Client: Wyeth Nutritionals (S) Pte Ltd and Wyeth Pharmaceuticals (S) Pte Ltd
Project: Wyeth Avserst 2000, Butritional Niro Spray Drying
Fabrication & Erection of All types of Stainless Steel Structures and Platform
Installation & Maintenance of Pumps, Equipment, Compressor and Heaters

Fabrication & Erection of All types of Stainless Steel Structures and Platform
Fabrication & Erection of Spray Dryer, Equipment for Nutritionals and Pharmaceuticals Factory

Unloading of Xylene Flash Pot, C-5650B


Moved into foundation by 100-ton crane


Positioning on anchor bolts


Xylene Flash Pot in its foundation
 

Client: EC Chemical Technologies Pte Ltd
Project: Speciality Chemical Skid Plant for China Research Institute of Daily Chemical Industry (RIDCI)
Completed Skid
Client: EC Chemical Technologies Pte Ltd
Project: Speciality Chemical Complex for CRODA Singapore Pte Ltd, Pulau Seraya
Piping Under Construction - Piperack

Reactor Module Lifting and Installation


Installation of Finished Product Tank Farm

Installation of Raw Material Tank Farm

Client: Degremont S.A.
Project: Waste Water Treatment Pant Facilities for Singapore Refining Company Pte Ltd
Preparation for Delivery of Pipe Spools

Pump Skid Design and Fabrication at Tuas Open Yard